Posted on May 14th, 2009 No commentsOn Saturday, we had a meeting to plan out the time frame for the next month leading up to the trip to MIT in June. We have five weeks left. The first three weeks will be devoted to building, the next week for testing, and the week school gets out for a final crunch. The week following, we will ship the finished project to MIT, and simply make sure our presentation is ready.
We also discussed some aspects of the presentation, i.e. videos, poster boards, and brochures.